Siyaram Kumar Yadav v. The Bihar State Power Holding Company Limited
Case brief
What is this about?
New electricity connection refused/not accepted in Rajiv Nagar, Patna; writ against South Bihar Power Distribution Company Limited and Bihar State Power Holding Company Limited officials; Clause 4.13(B) Chapter 4 Bihar Electricity Supply Code 2007; connection on encroached Government/Semi-Government/Public land; on-line application; direction to consider and decide within one month; petitioners to apply within 10 days; writ disposed with direction; Patna High Court; Justice Anil Kumar Sinha; order dated 06-03-2024; CWJC No.3095 of 2024.
What did the court decide?
Direction to the petitioners to submit on-line applications with all requisite documents within 10 days; on such submission, respondent nos. 4 and 5 to consider the applications in accordance with law and take an appropriate decision within one month. ¶26