Vishwa Ranjan Pandey v. The State Of Bihar and Ors.
Case brief
What is this about?
Petitioner sought mandamus for compensation for land under electricity transmission towers and crop loss at market value plus interest. The writ petition was disposed of in terms of the Court's earlier order in CWJC No. 8470 of 2022 (following the Supreme Court decision in Chairman Grid Corporation of Orissa Ltd. v. Sukmani Das), with liberty to approach the competent Civil Court for compensation; any such petition filed within four weeks was to be considered on merits and decided preferably within four months.
What did the court decide?
Liberty to seek compensation before the Civil Court within four weeks; such petition to be decided expeditiously, preferably within four months.