M/s Harsh Construction v. The State of Bihar
Case brief
What is this about?
A sand ghat lessee sought refund of a proportionate deposit paid for an eight-week extended mining period during which mining was stopped for want of environmental clearance. The High Court remitted the refund claim to the Managing Director of the Mining Corporation for fresh decision with personal hearing within fixed timelines.
What did the court decide?
Direction to respondent no. 4 to decide the refund representation afresh within three months with personal hearing; refund to be cleared within four weeks if allowed.