Dharma Nath Rai v. The State Of Bihar and Ors.
Case brief
What is this about?
In a writ petition, the Patna High Court directed the Circle Officer, Dariyapur, to conclude pending encroachment proceedings within six weeks by passing a final order under Section 6(1) of the Bihar Public Land Encroachment Act, 1956, after hearing affected parties, if not already done.
What did the court decide?
Direction to Respondent No. 4 to conclude proceedings within six weeks by passing a final order under Section 6(1) of the Bihar Public Land Encroachment Act, 1956.