Hemant Kumar Singh v. The State of Bihar
Case brief
What is this about?
Bank guarantee release after contract termination; whether defect liability period (Clause 74.0) survives termination of principal's contract; performance guarantee validity (Clause-9); stalled public-works contract, work stoppage 05.11.2019, re-design directive 06.05.2020, modification instruction 07.07.2021; 'Mandiri Nala', Patna Smart City Mission/Ltd; National Projects Construction Corporation Ltd.; price escalation and rate revision demand; liberty to invoke arbitration clause for unpaid dues; set-off for alleged defective work. Relevant to writ petitions seeking release of bank guarantees/performance guarantees where the overarching contract has been rescinded or terminated and work remains incomplete.
What did the court decide?
Writ petition allowed: 1st respondent directed to release the petitioner's bank guarantees within two weeks of uploading of the judgment; liberty reserved to the petitioner to recover other dues through appropriate remedy including the arbitration clause, with the respondent free to claim set-off for alleged defective work therein.