Md. Azimuddin v. The State of Bihar
Case brief
What is this about?
The High Court of Patna disposed of a writ petition challenging the quashing of a land compensation award under the 2013 Act. The court directed the Land Acquisition Authority to expeditiously dispose of the petitioner's objection under Section 21 within three months following due process under Section 23.
What did the court decide?
Direction to the Authority to dispose of the petitioner's objection under Section 21 of the 2013 Act expeditiously within three months.