M/s Vishal Construction v. The State Of Bihar and Ors.
Case brief
What is this about?
In a writ petition, the Patna High Court held that under the Standard Bidding Documents, the Engineer-in-Chief alone was the competent authority to grant an extension of time. The court quashed the Regional Officer's order rejecting the recommendation and remitted the matter to the Engineer-in-Chief within two months.
What did the court decide?
The impugned order dated 30.03.2018 was set aside and the matter remitted to the Engineer-in-Chief to take a decision within two months.