Bheem Prasad v. The State Of Bihar Through Principal Secretary Public Health Engineering Department Bihar Patna and
Case brief
What is this about?
This revision petition challenged an arbitration award dismissing a contractor's claim for unpaid dues and contract payments. The High Court admitted findings on work completion and time extension deductions but remanded the case for the Tribunal to decide on the refund of forfeited security and earnest money.
What did the court decide?
Civil revision petition disposed of partly; remanded to the Arbitration Tribunal for findings on refund of security deposit and earnest money.