Rajendra Prasad Singh v. The Union Of India and Ors.
Case brief
What is this about?
This writ petition sought a direction to repair and construct a segment of National Highway-30 between Mohania and Kra. The Court reviewed counter-affidavits stating that the project was transferred to NHAI, tenders were invited, execution followed the legal timeline, leading to the disposal of the petition by reiterating the statutory timeline for work completion.
What did the court decide?
Directed the concerned respondents (Respondents 1 and 6) to see to it that the road in question is constructed/repaired at the earliest as mentioned in the counter affidavit.