M/s Param Enterprises p Ltd. v. The Eastern Railways
Case brief
What is this about?
The Patna High Court allowed an appeal against an order dismissing a writ petition concerning contract price escalation. The court held that a modification in Railway Board policy removed the 5% minimum threshold for variation claims, entitling the contractor to the benefit.
What did the court decide?
Impugned order dated 5.8.2014 set aside; writ petition allowed; letter dated 12.4.2013 set aside; second respondent directed to examine claim per Annexure-1.