Debendra Rana v. State of Odisha
Case brief
What is this about?
Debendra Rana v. State of Odisha, W.P.(C). No.360 of 2026, High Court of Orissa at Cuttack, order dated 26.02.2026, coram K.R. Mohapatra and Sanjay Kumar Mishra, JJ. Enhancement of land acquisition compensation ordered on 20.09.2019 by Civil Judge (Senior Division), Bhawanipatna in LAR No.46 of 2019 (S.18 reference, Land Acquisition Act, 1984) not disbursed for six years; writ petition seeking sanction and disbursal disposed of with direction to Additional Chief Secretary, Water Resources Department to accord sanction by end of May, 2026 and release compensation with statutory dues by end of August, 2026. Keywords: compensation disbursal, sanction delay, LAR reference, Upper Indravati Irrigation Project, Kalahandi, Water Resources Department.
What did the court decide?
Direction to the Additional Chief Secretary, Water Resources Department, Government of Odisha, Bhubaneswar (Opposite Party No.1) to accord sanction for disbursal of the compensation in terms of the order dated 20th September, 2019 passed in LAR No.46 of 2019, as expeditiously as possible, preferably by end of May, 2026, and on receipt of such sanction, to release the compensation along with statutory dues in favour of the Petitioner on proper acknowledgement verifying entitlement, preferably by end of August, 2026.