Laxmi Hembram v. State of Odisha
Case brief
What is this about?
Orissa High Court; W.P.(C) No.308 of 2025; Laxmi Hembram v. State of Odisha and others; Subarnarekha Irrigation Project; R & R compensation claim Rs.7,72,425 with 18% interest from 07.02.2023; representation dated 04.11.2024; direction to decide representation (Annexure-7) within three months and communicate within two weeks; disposed without expressing opinion on merits; S.K. Sahoo and S.S. Mishra, JJ.; 28.01.2025.
What did the court decide?
Direction to opposite party no.3 (Project Director, R & R, Subarnarekha Irrigation Project, Laxmiposi, District-Mayurbhanj) to take a decision on the petitioner's representation vide Annexure-7 and pass appropriate order in accordance with law within three months from production of a certified copy of the order, and to communicate the order to the petitioner within two weeks of taking the decision; no adjudication of the compensation claim on merits.