M/S Aditya Enterpriser, Cuttack v. State of Odisha
Case brief
What is this about?
A mechanical contractor completed check dam work under an agreement, obtained a work completion certificate and fund allotment, but payment was withheld after a belated joint inspection alleged incomplete or defective work. The court held the objection was an afterthought and directed release of payment within four weeks.
What did the court decide?
Opposite parties directed to pay petitioner's dues per Annexure-3 allotment letter dated 12.04.2023 within four weeks.