Case brief
What is this about?
M/s. Balaji Melters Private Ltd., Angul v. CESU (now TPCODL), Khurda and others; W.P.(C) No. 151 OF 2014; High Court of Orissa, Cuttack; Justice K.R. Mohapatra; decided 06.01.2025; disposal of writ petition as withdrawal; provisional and final electricity assessment orders (Annexure-5, Annexure-12); appeal under Section 127 of the Electricity Act, 2003; condonation of delay dispensed with owing to writ pendency since 6 January 2014; two-week timeline for appellate authority; vacation of interim order in Misc. Case No.150 of 2014 dated 9 January 2014.
What did the court decide?
Writ petition disposed of as withdrawn; petitioner free to file an appeal under Section 127 of the Electricity Act, 2003 against the Final Assessment order; appellate authority directed to consider such appeal on merits within two weeks without insisting on a condonation-of-delay application; interim order dated 9th January, 2014 in Misc. Case No.150 of 2014 vacated; urgent certified copy to be granted on proper application.