M/S. Satya Sai Construction, Jajpur v. State of Odisha
Case brief
What is this about?
Orissa High Court, Cuttack; WP(C) No.14348 of 2025; M/s. Satya Sai Construction v. State of Odisha; writ of mandamus for release of admitted dues; consensual project closure letter dated 22.01.2025; H.L Bridge over Chingudia Nallah, 6 km Bari Binjharpur Road, Jajpur; National Waterway No.5 revised route; work completed Rs.125.71 lakhs unpaid; contract value Rs.574.25 lakhs; interest @6% from January 2025; default interest at RBI prime lending rate until actual payment; writ petition disposed of 28.07.2025.
What did the court decide?
Appropriate authority directed to release Rs.125.71 lakhs (after adjusting any amount already paid, if any) with interest @6% from January, 2025 till six weeks from the date of the order; timely payment bars further claims, failing which interest over and above the amount due at the RBI prime lending rate is payable until actual payment.