Post-remand re-examination (Orissa High Court, F.A. 168/1991, decided 12.11.2024 by Ananda Chandra Behera J.) of a State-of-Orissa construction-contract money-suit appeal (Upper Indravati Dam Project, Block No.18; contractor Santwant Singh Gill): uncovered/extra M-150 grade concrete works adjudged payable at the M-200 contract rate of Rs.190 per CuM on cost-parity, Chief Engineer opinion (Ext.S) and implied-acceptance grounds; idle-labour claim defeated by waiver/estoppel following extension of time to 02.08.1985; decree trimmed from Rs.7,03,375.29 to Rs.5,68,300.29 with interest unchanged; appeal partly allowed without cost. Themes: extra work beyond agreement, rate parity, idle labour/idle work, extension of time, estoppel/waiver, Supreme Court remand (Civil Appeal Nos.3113 & 3114 of 2006, Judgment dated 24.07.2006).
What did the court decide?
Appeal allowed in part on contest without cost: the Trial Court's idle-labour award of Rs.1,35,075/- is set aside and deducted from the principal decreetal amount, leaving a revised principal decreetal amount of Rs.5,68,300.29/- carrying the same interest terms as originally decreed; the plaintiff-contractor's entitlement to Rs.190/- per CuM for the M-150 Grade works (differential Rs.1,22,253.03 paisa per the Trial Court findings) stands confirmed.