Executive Enginr., Tpsodl, (Erstwhile Southco), Berhampur v. M/S. United Electricals and Engineering Pvt. Ltd.
Case brief
What is this about?
Orissa High Court, Cuttack; ARBA No.9 of 2024; Dr. Justice S.K. Panigrahi; arbitration appeal; RFA No.54 of 2023; District Judge Ganjam; dismissal on limitation; remand to Commercial Court; MSEFC Case No.22 of 2020; Micro and Small Enterprises Facilitation Council Cuttack; award dated 27.12.2022; TPSODL Berhampur; Executive Engineer; M/s. United Electricals Engineering Pvt. Ltd.; order dated 07.05.2024 set aside; time-bound adjudication (one month transmission, two months completion); sympathetic consideration of delay.
What did the court decide?
ARBA No.9 of 2024 disposed of: impugned order dated 07.05.2024 set aside; District Judge, Ganjam directed to transmit RFA No.54 of 2023 record to the concerned Commercial Court within one month; Commercial Court to decide on merit uninfluenced by the set-aside order, treating the appellants' delay sympathetically, and complete the proceeding within two months of transmission.