Madan Mohan Nayak v. Deoranjan Kumar Singh
Case brief
What is this about?
In a contempt application regarding non-compliance of an order for service regularization and financial benefits, the court directed the petitioner to resubmit documents. The authorities were given six weeks to settle the claim thereafter, and the petition was dropped with leave to revive.
What did the court decide?
Petitioner directed to resubmit documents in two weeks; respondent to settle claim within six weeks; petition dropped with liberty to revive.
What the court decided
IN THE HIGH COURT OF ORISSA AT CUTTACK
CONTC No.4343 of 2021
Madan Mohan Nayak
Petitioner
Mr. K.P. Mishra, Senior Advocate
-versus-
…. Opposite Parties/ Contemnors
Deoranjan Kumar Singh, Principal Secretary, Government of Odisha, Panchayatiraj Department, Odisha, Secretariat Building, Bhubaneswar and others.
Mr. Saswat Das, A.G.A.
CORAM: JUSTICE A.K.MOHAPATRA
ORDER
15.12.2023
Issues for consideration
1 issue framed by the court
Whether the petitioner should be directed to resubmit documents to enable the respondent authorities to process the claim for regularization and financial benefits.
Parties & counsel
- petitioner
Madan Mohan Nayak
- respondent
Deoranjan Kumar Singh
Coram
A.K. Mohapatra
Case details
As recorded by the court registry
Similar cases
Judgements on the same questions, provisions and authorities, from every court