21st October, 2016 for value of Rs.27,00,01,000.00 and completion certificate dated 27th September, 2019 for original contract value of Rs.25,43,15,588.00 and executed value of Rs.25,96,99,318.00 in support of completion of similar work by the Petitioner. After the technical bids of the bidders were opened on 3rd January, 2020, the same was scrutinized by the Scrutiny Cell where after deficiencies of the respective bidders were informed to them vide e-mail on 31st January, 2020 for submitting clarificatory/deficient information and documents by 5th February, 2020 through e-portal. Since the amount mentioned in the completion certificate submitted by the Petitioner did not match with the LOA submitted by it, it was specifically informed to submit the copy of the work order and schedule of quantity for the work done amounting to Rs.25,96,99,318.00 together with history and structure of the firm, name of the Director/Partners/Proprietor with technical staff before 5th February, 2020. The Petitioner in response to the same submitted voluminous papers through e-portal on 4th March, 2020. Since there was a mismatch in the first and last page of the schedule of quantities for Rs.27,00,01,000.00 and abstract of payments including the 12th and final bill for the work done amounting to Rs.25,96,99,318.00, the technical bid of the Petitioner was rejected. It is his submission that not only the schedule of quantities of the completed work for Rs.27,00,01,000.00 remained incomplete but also no such schedule of quantities for Rs.25,96,99,318.00 as called from the Petitioner was submitted. Accordingly, the TEC evaluated the technical bids of the bidders on 10th February, 2020 which came to be compiled on 21st February, 2020 as per the note sheet attached to the writ petition as Annexure-5. On consideration of the bids submitted by Opposite Party No.7, namely, M/s. B.C.Bhuyan Constructions Private