United Construction v. C.G.M.,Office of the Principal Chief Engineer
Case brief
What is this about?
This disposal concerns a Section 11 application for appointment of an arbitrator under the Arbitration and Conciliation Act, 1996. The High Court held that since the claim was manifestly time-barred with no explanation for the delay, the petition was dismissed without referring the matter to arbitration.
What did the court decide?
Petition for reference to arbitration dismissed; no order as to costs.