M/S.Bigyan Construction Pvt.Ltd v. State of Odisha
Case brief
What is this about?
The High Court disposed of a writ petition where a construction company sought directions to exclude a stalled road project from its bid capacity assessment due to delayed site handover and clearances, directing the respondent department to expedite consideration.
What did the court decide?
Writ petition disposed directing the Works Department to consider the petitioner's representation and pass a reasoned order within two weeks.