Subrata Kumar Satapathi v. National Highway Authority of India,Piu
Case brief
What is this about?
The High Court disposed of a writ petition seeking direction for land acquisition compensation. The court directed the petitioner to file a claim application with the designated Tahasildar within two weeks, noting that the statutory process must then be completed within three months.
What did the court decide?
Petitioner directed to file claim application before Tahasildar-cum-Land Acquisition Officer within two weeks; authority to decide within three months.