Pyarimohan Pradhan v. State of Orissa
Case brief
What is this about?
Allowed.
What did the court decide?
The condition in Para-3.5.5(v) of Note-II of OPWD Code Vol. 1 mandating APS at the time of bid submission was quashed.
What the court decided
W.P.(C) No. 18535 of 2017
02. 01.09.2017 Learned counsel for the parties agree that the issue
involved in this writ petition with regard to Office Memorandum dated 04.05.2016 issued by the
Works Department of the Government of Odisha is identical to one involved in W.P.(C) No. 7120
of 2017 and it is, thus, contended that this writ petition may be disposed of in term of the
said judgment.
Accordingly, for the reasons given in the judgment dated 24.07
.2017 passed in W.P.(C) No. 7120 of 2017 (Ajay Kumar Jain vs. State of Odisha and others), thi
s writ petition also stands allowed to the extent that the condition imposed by Office Memoran
dum dated 04.05.2016 by amending Para-3.5.5(v) of Note-II of OPWD Code Vol. 1 by modifying the
same and providing that Additional Performance Security (APS) of the amount of difference bet
ween the estimated cost and the cost of bid (if lower than the estimated cost) is to be provid
ed at the time of submission of the bid, is quashed.
The said condition of providing Additional Performance Securit
y of the amount of difference can be imposed only for a successful bidder which can be require
d to be provided within such stipulated time as may be provided for, or else the bid of the su
ccessful bidder would be cancelled and the security deposit would be forfeited, if permissible
in law, and further proceeding for blacklisting would be initiated as per law.
We make it clear that we are not expressing any opinion with r
egard to Office Memorandum dated 08.11.2013 or with regard to other prayers made in the writ p
etition, as the prayer for quashing the Office Memorandum dated 04.05.2016 alone has been cons
idered. No order as to costs.
This writ petition thus stands disposed of.
Issues for consideration
2 issues framed by the court
Whether the condition requiring Additional Performance Security from all bidders instead of only successful bidders under the Odisha Works Department guidelines is legal.
Whether the writ petition challenging the parameters in Office Memorandum dated 04.05.2016 should be disposed of in the terms of W.P.(C) No. 7120 of 2017.
Parties & counsel
- petitioner
Petitioner
- respondent
State of Odisha