In the matter of Shirdi Industries Limited [Ia No. 2187 of 2020, Ia No. 320,340 & 1534 of 2021 in Cp(Ib) No. 839 of 2017]
Case brief
What is this about?
The NCLT addressed disputes over pre- and post-CIRP electricity dues between a resolution applicant and power corporations. The court held that post-commencement payments must be adjusted against CIRP dues, and pre-CIRP dues must be paid per the resolution plan. It clarified that statutory dues arising after plan approval are extinguished by the plan.
What did the court decide?
Pre-CIRP dues to be paid per resolution plan; CIRP period dues from payments made post-commencement; no disconnection for pre-CIRP dues; electricity connection to be restored.