In the matter of Shiv Mfg. Pipes Pvt. Ltd. [I.a. 1202 of 2022 in C.P. (Ib) 3749 of 2018]
Case brief
What is this about?
The NCLT Mumbai Bench allowed an application to condone a three-day delay in filing a claim before the liquidator under Section 42 of the IBC. The court held the delay was not willful and directed the liquidator to verify and pass an order on the claim.
What did the court decide?
The Application was allowed; the Liquidator was directed to verify and pass an appropriate speaking order on the Applicant's claim.