In the matter of Manpasand Beverages Limited [CP-IB-847-AHM-2019]
Case brief
What is this about?
This judgment admits an application by an operational creditor to initiate the Corporate Insolvency Resolution Process against the respondent corporate debtor. The Tribunal found that the debt and default requirements under Section 9 were satisfied, declared moratorium under Section 14, and appointed an Interim Resolution Professional.
What did the court decide?
Application admitted; MORATORIUM declared under Section 14; Mr. Ajay Kumar Milhotra appointed as IRP; Advance of Rs. 2,00,000 directed to be paid to IRP.