From the communications, it is cleared that the Operational Creditor rescind the contract by refusing to carry out work in terms of LOI. All this process caused time and money. The Operational Creditor denied to carry out work upon receipt of approved FQAP and drawings and started demanding more money. Thereafter revised offer dated 18.10.2018 for Rs. 6,45,00,000 plus taxes for updated BOQ was submitted by the Operational Creditor whereas work was for much less amount i.e. around Rs. 5,30,00,000/-. The Operational Creditor claimed 30 days period for mobilization after receiving LOI which shows that there was no mobilization from the side of Operational Creditor at the site. There is no unpaid operational debt and Operational Creditor is not entitle to claim anything. The papers and documents submitted are not verified or certified by site incharge. Vide communications dated 30.04.2019, 01.02.2019 & 26.11.2018, it is cleared that there is an admitted and existing dispute between the parties (Annexure-8).