In the matter of Grj Distributors and Developers Pvt. Ltd. IA-1644-2023 in Cp (Ib) – 477(ND)-2021
Case brief
What is this about?
In an application under Rule 11 of NCLT Rules, 2016, allottees sought clarification that the Insolvency and Bankruptcy Code CIRP and moratorium initiated against M/s. GRJ Distributors and Developers Pvt. Ltd. applied only to the Avalon Rosewood project, not the corporate debtor as a whole. The Tribunal allowed the application and issued a corrected order limiting CIRP and moratorium to the specifi
What did the court decide?
Application allowed; order corrected to limit CIRP and moratorium to the Avalon Rosewood project of the Corporate Debtor.