In the matter of M.P. Enterprises & Associates Ltd. [I.a. No. 3990 of 2023 in C.P. No. 64-2023]
Case brief
What is this about?
In an insolvency proceeding, a creditor sought condonation of a 92-day delay in filing a claim against a corporate debtor after the circular resolution process commenced. The NCLT held the delay was unintentional and reasonable, allowing the application and directing the Resolution Professional to admit the claim.
What did the court decide?
Condonation of 92-day delay in submission of the Applicant's claim; Direction to Resolution Professional to adjudicate upon the claim on its merits.