What is this about?
The Tribunal allowed an interim application by the IRP to withdraw the CIRP order against Nicotra India Pvt Ltd. The court held that since dues were settled with the Operational Creditor and CIRP costs were paid, withdrawal was appropriate without COC approval as it had not yet been constituted.
What did the court decide?
CIRP order dated 18.01.2022 against the Corporate Debtor is withdrawn, relieving the debtor from moratorium; application disposed of.