In the matter of Ecogreen Energy Lucknow Private Limited Cp (Ib) No. 65-Chd-Hry-2019
Case brief
What is this about?
The NCLT Chandigarh Bench dismissed a petition under Section 9 of the IBC, 2016 seeking CIRP against Ecogreen Energy. The court held that a pre-existing dispute over defective machinery supply and breach of contract, evidenced by prior warnings, existed and thus the petition lacked merit.
What did the court decide?
The Corporate Insolvency Resolution Process against M/s Ecogreen Energy Lucknow Private Limited was not initiated as the petition was dismissed.