In the matter of Utm Engineering Private Limited [Company Petition No. IB-248/ND/2019]
Case brief
What is this about?
The NCLT admitted an application under Section 9 of the IBC, 2016 filed by Argentium International Pvt Ltd against UTM Engineering Pvt Ltd for initiating CIRP. The Court rejected the debtor's dispute defenses and force majeure claims, finding a default occurred. The court appointed an Interim Resolution Professional and directed the appointment of an IRP.
What did the court decide?
The application was admitted under Section 9(5); moratorium under Section 14 took effect; Mr. Rajesh Jangra appointed as Interim Resolution Professional.