Rainbow Environments Pvt. Ltd. v. Ministry of Environment Forest and Climate Change
Case brief
What is this about?
The National Green Tribunal dismissed an appeal challenging environmental clearance conditions. The court directed the SEIAA, Punjab to incorporate requisite safeguards via the SPCB within three months per the 2024 SOP but otherwise dismissed the challenge, noting existing writ petitions govern the clearance.
What did the court decide?
Directed SEIAA, Punjab to incorporate safeguards from SPCB within 3 months via SOP.