2. In compliance with the above-said directions, the Commissioner – Pallipalayam Municipality has filed its status report dated 03.12.2024, stating that due to sewage and dye waste contamination, the Pallipalayam Municipality was fined Rs.1.05 Crore, of which, Rs.10 lakh has been paid. Further, an estimated cost of Rs.10.79 Crore DPR under Swachh Bharat Mission (SBM 2.0) for an STP using Soil Bio-Technology (SBT) was approved by the Directorate of Municipal Administration, Chennai, and work was awarded to M/s. Poorani & Co. on 05.05.2023. Initially, sites at Cauvery Riverbank (1.50 MLD) and Periyar Nagar (3.50 MLD) were selected, but inspections on 21.06.2023 and 20.07.2023 deemed them unsuitable, as they were in the river course. Accordingly, a new site 6 km away in Elanthakuttai Village (20.36 acres) was identified, but strong public opposition delayed progress. Peace meetings on 02.02.2024, 06.02.2024, and 14.02.2024 failed to resolve concerns over livelihood impact, agricultural pollution, and air quality. A high-level meeting on 19.02.2024 reaffirmed the project’s necessity. Due to continued resistance, the project reverted to Periyar Nagar, requiring an additional Rs.19 Crore for sewage transport infrastructure. The DRO approved the site, encroachments were cleared, and construction of a 3.50 MLD STP began on 11.11.2024. Currently, earthwork is in progress, but hard rock at 1.80 meter depth