Sayyed Mohammed Sabir Usman v. Union of India through Secretary Ministry of Environment Forest & Climate Change
Case brief
What is this about?
The NGT addressed allegations of environmental violation regarding a real estate project, examining if construction of an additional building constituted a scope change. The Tribunal found no EC violation but directed the installation of an Organic Waste Convertor and solar system, levied environmental compensation for STP non-operation, and exempted Consent to Establish revalidation.
What did the court decide?
Respondent to install OWC and solar system within 6 months with Bank Guarantee; deposit Rs. 2.02 crore as environmental compensation for STP non-operation.