Shri Shanlang W Kharbangar v. Meghalaya Pollution Control Board
Case brief
What is this about?
The National Green Tribunal dismissed an application challenging an Environmental Compensation demand. The court rejected claims of confusion between the initial and revised compensation amounts, noting the respondent had revised the demand to Rs. 75,000. The tribunal granted the applicant 15 days to deposit the reduced amount.
What did the court decide?
Original application dismissed with liberty to deposit the Environmental Compensation of Rs. 75,000 within 15 days.