Rustom Jehangir Cama v. Ministry of Environment Forest and Climate Change
Case brief
What is this about?
The National Green Tribunal, Central Zone Bench, Bhopal, disposed of two original applications concerning illegal construction, encroachment, and violation of the Zonal Master Plan in Mount Abu. The court noted the High Court had already decided the matter and the revised Zonal Master Plan-2030 was notified, directing petitioners to file fresh applications.
What did the court decide?
Petitioners directed to file applications for construction permission within one week; Municipal Board directed to decide within four weeks; petitions disposed of in light of High Court order.