Samir Bapodra (Partner of Tapi Stone Quarry) v. State Environment Impact Assessment Authority Gujarat
Case brief
What is this about?
The National Green Tribunal dismissed an appeal and a delay condonation application as time-barred. The Tribunal held that the appeal, filed on 04.10.2025 against an order passed on 30.12.2024, violated the limitation period under Section 16 of the National Green Tribunal Act, 2010.
What did the court decide?
The appeal and the application for condonation of delay (I.A. No.818 of 2025) were dismissed as time-barred.