“19. The limitation as prescribed under Section 16 of the NGT Act, shall commence from the date the order is communicated. As already noticed, communication of the order has to be by putting it in the public domain for the benefit of the public at large. The day the MoEF shall put the complete order of Environmental Clearance on its website and when the same can be downloaded without any hindrance or impediments and also put the order on its public notice board, the limitation be reckoned from that date. The limitation may also trigger from the date when the Project Proponent uploads the Environmental Clearance order with its environmental conditions and safeguards upon its website as well as publishes the same in the newspapers as prescribed under Regulation 10 of the Environmental Clearance Regulations, 2006. It is made clear that such obligation of uploading the order on the website by the Project Proponent shall be complete only when it can simultaneously be downloaded without delay and impediments. The limitation could also commence when the Environmental Clearance order is displayed by the local bodies, Panchayats and Municipal Bodies along with the concerned departments of the State Government displaying the same in the manner afore- indicated. Out of the three points, from which the limitation could commence and be computed, the earliest in point of time shall be the relevant date and it will have to be determined with reference to the facts of each case. The applicant must be able to download or know from the public notice the factum of the order as well as its content in regard to environmental conditions and safeguards imposed in the order of