Kasim Alayan v. the Water/Air Appellate Authority
Case brief
What is this about?
Appeal against withdrawal of 'Consent to Operate' for a saw mill due to alleged increase in power capacity and failure to maintain siting criteria. NGT directed the PCB to re-inspect and issue consent if compliant, allowing operation while imposing liability for the power increase violation.
What did the court decide?
Issue CONSENT TO OPERATE after re-inspection within 6 weeks; PCB may impose damages for unauthorized power increase.