Vennimalai v. The Chief Engineer
Case brief
What is this about?
Agricultural electricity service connection; TANGEDCO/TNEB Tirunelveli; disconnection after sanction due to irregularities by officials; disciplinary action against officials; prayer for restoration or refund of Rs.2,50,000/-; representation dated 12.01.2026; writ of Mandamus; Article 226 Constitution of India; direction to Superintending Engineer to consider representation on merits within four weeks; writ petition disposed of; no costs; Madurai Bench of Madras High Court; Hemant Chandangoudar, J.; Kadayanallur Taluk; Tenkasi District; Survey Nos.505/2A and 3, Muthusamypuram.
What did the court decide?
Direction to the second respondent to consider the petitioner's representation dated 12.01.2026 on its own merits and in accordance with law and pass appropriate orders within four (4) weeks; no costs. Restoration of the connection and refund of Rs.2,50,000/- were not ordered by the Court at this stage.