M.Alagarsamy v. The Commissioner
Case brief
What is this about?
Unauthorized construction without planning permission; removal/demolition notice dated 03.02.2026 (Na.Ka.No.Ma2E/1960/24) by Madurai City Municipal Corporation; belated regularization/rectification application dated 27.01.2026; writ of certiorarified mandamus under Article 226; writ petition dismissed, no costs; connected W.M.P.(MD) No.2872 of 2026 closed; Madurai Bench of Madras High Court; W.P.(MD) No.3500 of 2026; Bench of Dr.Justice G.Jayachandran and Mr.Justice K.K.Ramakrishnan.
What did the court decide?
Because the petitioner constructed without obtaining planning permission and applied for rectification only after the respondents took steps for removal of the unauthorized portion, the Court was not inclined to entertain the writ petition. ¶¶24