Case brief
What is this about?
S.Thangavel v. Managing Director / General Manager, Tamil Nadu State Transport Corporation (MDU) Ltd., W.P.(MD) No.16934 of 2026, Madurai Bench of Madras High Court, decided 19.06.2026 by Mummineni Sudheer Kumar, J. Interest on delayed payment of terminal benefits; 6% per annum from date of retirement till actual payment; compliance within five months; disposed at admission stage with consent; issue held squarely covered by W.A.(MD) No.403 of 2010 batch (19.06.2014) and W.A.(MD) No.1419 of 2021 batch (26.07.2021); Article 226 mandamus; no costs.
What did the court decide?
Respondents directed to pay interest at 6% per annum on the petitioner's terminal benefits from the date of retirement till the date of actual payment, compliance within five months from receipt of a copy of the order; no costs. ¶27