Keywords: Madras High Court; WP No. 8474 of 2026; writ petition; Sri Aandavar Constructions; Partner Maheshwaran; C.Prakasam; District Collector Tiruppur; Assistant Director of Panchayat Collectorate; Block Development Officer Kundadam Panchayat Union; Special Officer Gethalrev Village Panchayat; C.Meera Arumugam AGP; G.Nanmaran SGP; borewell; tender; payment disbursement; Rs.4,18,938; 12 weeks; no costs; Joint Director of Rural Development; Abdul Quddhose J.; order dated 06-03-2026.
What did the court decide?
Third respondent directed to release payment of Rs.4,18,938/- to the petitioner for the works done by him within 12 weeks from the date of receipt of a copy of the order; no costs. ¶28