M/s.Sri Srinivasa Engineering v. State of Tamil Nadu
Case brief
What is this about?
SIPCOT industrial plot allotment and 99-year lease; penalty for non-implementation of project; COVID-19-induced delay in construction; State Industries Promotion Corporation of Tamil Nadu Limited (SIPCOT) demand of Rs.20,09,127/- inclusive of GST Rs.3,06,000/- plus processing fee Rs.11,800/-; extension of project implementation period from 30 to 60 months; surrender of plot on payment default; writ of certiorarified mandamus under Article 226; disposed with direction to pay by demand draft within six weeks. Keywords: SIPCOT Vallam Vadagal; Plot G-112/1; lease deed 04.01.2019; non-implementation penalty; O.O.43; O.O.No.37.
What did the court decide?
Writ petition disposed with a direction to the petitioner to remit Rs.20,09,127/- (penalty inclusive of GST) together with processing fee of Rs.11,800/- by demand draft in favour of the 2nd respondent within six weeks; on remittance the respondents to accept and proceed in accordance with the lease deed dated 04.01.2019; on default, petitioner to surrender the land; no order as to costs; connected Miscellaneous Petition closed.