Sri Rangavilas G.S. and W.Mills v. the Recovery Officer
Case brief
What is this about?
ESI dues recovery demand Rs.36,16,435 by ESIC Recovery Officer Coimbatore; writ of certiorari under Article 226 dismissed for bypassing statutory remedy; Section 75 Employees' State Insurance Act; Employees' Insurance Court competent forum; alternative-remedy bar to writ jurisdiction; RRC/SRO recovery proceedings No.56-00-005943-000-0101 and CBE/RECY/CP-4 consequential order; Indian Overseas Bank Peelamedu branch; three-week moratorium on coercive recovery; National Textile Corporation mill unit petitioner; Madras High Court, K. Surender J., 21-07-2026.
What did the court decide?
Writ petition dismissed; petitioner granted liberty to approach the Employees' Insurance Court; no coercive action for three weeks from receipt of a copy of the order; connected miscellaneous petitions (WMP Nos.30395 and 30397 of 2026) closed; no costs. ¶23