Gopalakrishnan v. the Union of India
Case brief
What is this about?
Project Tiger Scheme rehabilitation package; revised guidelines February 2008; Option I monetary compensation Rs.10,00,000/- per family; eligible beneficiary; cut-off dates 31.12.2010 and 01.01.2014; Mudumalai Tiger Reserve; Mudumalai Village relocation; RTI disclosure contradicting State counter affidavit; certiorarified mandamus; Article 226 Constitution of India; Revenue Divisional Officer Gudalur proceedings quashed; Union of India directed to disburse compensation; Madras High Court; Hemant Chandangoudar J.; WP No. 10064 of 2025; order dated 13-07-2026.
What did the court decide?
Writ petition allowed; proceedings dated 03.07.2024 of the seventh respondent set aside; seventh respondent directed to forward the proposal to the first respondent within four weeks; first respondent directed to disburse Rs.10,00,000/- to the petitioner within a further period of six weeks; no order as to costs.