V.Subramaniyan v. The Branch Manager
Case brief
What is this about?
Condonation of delay: Madras High Court, Justice M. Dhandapani, order dated 30-03-2026 on WMP No. 13374 of 2026 in WP SR No. 56101 of 2025. Petitioner V. Subramaniyan (counsel Mr. S. Arunachalam); respondents: Branch Manager, Punjab National Bank, Trichy Main Road, Trichy, and Deputy General Manager, Punjab National Bank, Circle Office (HRD), Coimbatore. A delay of 322 days in representing the writ petition was condoned under Order IV Rule 9(4) of AS Rules and the petition ordered; Registry directed to number the petition if otherwise in order. No precedents cited; no monetary quantum involved.
What did the court decide?
Delay of 322 days in representing writ petition SR.56101 of 2025 condoned and the petition ordered; Registry directed to number the present petition if otherwise in order. ¶22