A.Nalluchamy, v. Chandrasekaran
Case brief
What is this about?
Madras HC (Madurai Bench) allows S.A.(MD)141/2018 (K.K.Ramakrishnan J., 21.01.2026): common compound wall between TNHB 'L'-type houses inferred from sale-deed fences/appurtenances clause (Ex.A1), D.W.1 admissions and Housing Board norms; injunction suit maintainable without declaratory relief; concurrent dismissals by Additional District Munsif, Karur and Principal Sub Court, Karur interfered with under S.100 CPC; permanent injunction granted, mandatory injunction declined (construction removed during suit); parties to keep common wall ('B' schedule) unchanged.
What did the court decide?
Second Appeal allowed: permanent injunction restraining the defendant from putting up any further construction on the common compound wall; both plaintiff and defendant directed to keep the common compound wall ('B' schedule property) as such without any further construction or demolition; mandatory injunction (removal/demolition) not granted as the defendant removed the construction during the suit; no order as to costs; connected miscellaneous petition C.M.P.(MD).No.3759 of 2018 closed.