G.Ravichandran v. the Special Officer
Case brief
What is this about?
Madras HC, P.B. Balaji J., CRP No.6233 of 2025, decided 06.02.2026 (reserved 29.01.2026). Keywords: Article 227 revision; condonation of delay; 2207 days' delay in re-presenting restoration petition; appeal CMA (CS) No.37 of 2004 dismissed for default 19.12.2007 against Deputy Registrar (Housing) order; condone-delay application returned 04.06.2016 and 05.01.2017; fault of Advocate's clerk; petitioner not to suffer for clerk's oversight; liberal view of delay limited to re-presentation of papers; Court below wrongly weighed original restore application; prejudice to respondent compensated by costs Rs.20,000/- payable within four weeks; District Judge Salem to dispose main appeal within six months; respondent Salem Cooperative Housing Society Ltd (S-1329); advocates S. Ayyathurai (petitioner), B. Tamil Nidhi (respondent); no precedent cases cited.
What did the court decide?
Civil Revision Petition allowed; order of the Principal District Judge, Salem in I.A. No.1 of 2023 in CMA (CS) No.37 of 2004 dated 11.11.2024 set aside, conditional on payment of Rs.20,000/- costs to the first respondent Society within four weeks; upon compliance, the District Judge to formally allow the restoration application and expedite disposal of the main appeal within six months; no costs imposed on the CRP itself.